In April 2025, the DASA Project reached new milestones in its implementation. After many months of earthworks and excavation, followed by the erection of steel framework, concrete pouring has begun at the sulfuric acid plant construction sites in the smelter, furnace, and sulfur filter areas, as well as at the plant’s process control laboratory construction site.

Similarly, work on the camp extension is progressing rapidly, with more than 75% of the 250-bed “Camp Lida” construction site now complete, following the commissioning of 60 senior rooms in March 2025.